Case Study - Link Laters
Client:LinkLaters
Project:Milton House
Market:Law
Date:2005 
Equipment:

XS 1000k Openset Acoustic Enclosure
65dBa @1m Freefield between bulk tank in basement and roof.

1 x XS1000K Standby LV Diesel generating set G3 installed on roof level 16 arranged for Automatic start from receipt of remote start signals  and serving TP5 & TP6.

The generator is housed within an Acoustic enclosure designed to reduce noise levels to 65dBA @ 1M Free-field.  The generator is fed from an adjacent 1200Litre daily service tank installed within a 4-hour fire rated enclosure.  Fuel to the Daily service tank is supplied from an existing 20,000 Litre bulk fuel tank on the Mezzanine Floor via an new AVK fully automatic Duplex fuel transfer pump system.

 

Click here to view our other case studies

 





Search Site
Products & Services

Uninterruptible Power Supplies
Standby Generators
Generator Hire
Protection Relays
Turnkey Power Solutions
Switch Gear

Recruitment
Click here for career opportunities with AVK | SEG (UK)

Client Testimonals.